Key Bridge rebuild: Joseph B. Fay wins $38.6 million contract to clear the old bridge from the Patapsco
The Maryland Transportation Authority on Thursday handed a $38.6 million contract to Joseph B. Fay Company, an S&B USA Construction business, to tear out what remains of the Francis Scott Key Bridge in Baltimore's Patapsco River.
Fay's price was far below the owner's own number. MDTA board documents put the estimate at close to $92 million, WMAR 2 News reported, and the authority said the job went to the lowest-priced qualified bidder after bids came in at the end of October. Notice to proceed is expected in December, with 671 calendar days to finish. Fay previously teamed with Skanska on Baltimore's Howard Street Tunnel.
Under the contract, crews will lift out and salvage the steel girder spans still standing near both shores, knock down eight marine piers, fully remove two land piers, demolish nine foundations below the waterline and clean out 96-inch steel pipe piles so they can be filled with concrete for the new bridge, according to MDTA. The land side was cleared in February, when more than 20,000 tons of decking, columns and girders came out.
This is the first of four packages Maryland is buying separately since it dropped Kiewit Infrastructure in April, after the two sides failed to agree on terms for building the bridge. Kiewit had designed the replacement. The main span and marine approaches were advertised in July, with work set to start next summer. The south land approach goes out to bid late this fall or early winter and the north approach in winter 2027, The Daily Record reported.
The new crossing will be Maryland's first cable-stayed highway bridge: two lanes each way, a main span of 1,665 feet and no less than 230 feet of vertical room above the shipping channel. MDTA puts the cost at $4.3 billion to $5.2 billion and still aims to open it to traffic in 2030. The old bridge fell in March 2024 when the cargo ship Dali struck it, and six construction workers died.
Why it matters: Fay will be lining up marine demolition, crane, diving and steel salvage work for a December start. A winning bid at well under half the owner's estimate also sets expectations for the three larger Key Bridge packages still to be bid.
Sources
- MD awards demolition contract in Key Bridge rebuildThe Daily Record, Nov 19
- Key Bridge rebuild moves ahead as MDTA awards $38.6M demolition contractFox Baltimore, Nov 19
- Maryland awards $38.6M contract to remove remaining Key Bridge structures from Patapsco RiverWMAR 2 News, Nov 19