I.PARK1 incinerator fire in Hong Kong likely started by welding or smoking; full operation delayed
The Oct. 26 fire at I.PARK1, Hong Kong's first waste incinerator, on an artificial island off Shek Kwu Chau, was likely caused by welding work or smoking, the Fire Services Department found. Environment Secretary Tse Chin-wan told lawmakers on Nov. 18 that full operation will be pushed back.
The No. 3 alarm fire broke out at about 12:40 p.m. on or near the roof of the third of the plant's three incineration modules, where welding and other finishing work was still under way, according to Tse's written reply to the Legislative Council. It was largely out by 4:45 p.m. About 970 construction workers and plant staff were evacuated from the island. Investigators ruled out electrical faults, arson and chemicals igniting on their own.
The fire damaged the aluminium cladding on the roof sheets, the steel members carrying the roof, and ventilation, ducts and piping in the third module. The other two modules, the waste bunkers and the unloading hall were untouched, and the first two modules went back into testing from Oct. 30. A registered structural engineer hired by the contractor found no imminent danger to the building. The plant had just about reached its design capacity of 3,000 tonnes of municipal waste a day on Oct. 23; its waste now goes to the West New Territories Landfill Extension.
Under the contract, the contractor pays for damage that happens before formal operation and carries contractor's all-risks insurance, the government said. No date has been set for finishing repairs. The plant was due to reach full operation in 2026.
The contractor has banned smoking across the site since January 2026. Workers leave cigarettes and lighters at the pier before boarding for the island, and a subcontractor is fined HK$3,000 for each cigarette butt or pack found in its area. Since January the contractor has removed nine workers caught smoking from the project and fined subcontractors 59 times, about HK$810,000 in all. Subcontractors that fail its half-yearly safety reviews are barred from bidding on its future projects.
Why it matters: One hot-work spark or cigarette on a roof during finishing work knocked a third of a nearly finished plant offline. Main contractors now push hot-work permits, smoking bans and per-violation fines down to subcontractors, and subs should read those clauses before pricing a job.