Google data center in Belgium: why did Wallonia halt construction at Farciennes?
Inspectors from Belgium's Wallonia region ordered Google to stop work at its Farciennes data center site near Charleroi on Nov. 26, after finding a nearly finished 30,000-square-meter building that relies on a permit change the regional minister refused in August.
About 300 workers were on the site when inspectors arrived on Thursday, Raphaël Stokis, the region's delegated planning official, told public broadcaster RTBF. The building covers 3 hectares and its shell was already closed. Inspectors gave a verbal stop order, which Stokis said will be confirmed to Google in writing. Entrevue reported that the regional administration called it a major violation and said an official report would go to prosecutors.
The dispute is about water. Google, which builds the campus through its European subsidiary Crystal Computing on the 53-hectare Ecopôle business park, won a permit in 2024 for three air-cooled data centers. It then asked to merge two of them into one larger building and cool it with water drawn from the Sambre river. The Walloon administration approved that change in April 2026, a citizen appealed, and in August planning minister François Desquesnes refused it, citing drought risk. According to the minister, the plan called for taking 600 cubic meters of water an hour from the river, with less than a quarter returned.
Google has appealed the refusal to the Council of State, Belgium's top administrative court, which hears the case on Jan. 7, 2027. Greenpeace Belgium had filed an urgent request a day before the inspection, using satellite images to show the work had continued. In a short statement to RTBF, Google said it is committed to open and collaborative dialogue with the regional government on its Walloon investments.
Farciennes is Google's second Belgian campus. Construction began in April 2024 as part of a 1 billion euro investment, The Brussels Times reported, with about 100 permanent jobs planned. Its first Belgian data center, at Saint-Ghislain near Mons, has run since 2010 and employs more than 400 people.
Why it matters: Building ahead of a permit change that is still under appeal can leave a GC with a closed-in shell, 300 workers sent home and possible criminal referral. On data center jobs, check which approved permit the drawings you are building actually match.
Sources
- Google invests €1 billion in new data centre in poorest Walloon areaThe Brussels Times, Apr 7, 2024
- Google introduit un recours au Conseil d'État pour son site de FarciennesDH Les Sports+ (Belga), Oct 28
- Farciennes : Google poursuit les travaux d'un data center sans permis adéquat, dénonce GreenpeaceRTBF, Nov 25
- Google contraint d'interrompre les travaux de son second data center sur le chantier de Farciennes/Aiseau-PreslesRTBF, Nov 26
- Belgique : Google contraint d'interrompre la construction d'un centre de données faute de permisEntrevue, Nov 27