Gateway Hudson Tunnel Project starts boring its second tube under the Palisades

The second tunnel boring machine on the $16 billion Hudson Tunnel Project has started mining the southern tube in North Bergen, New Jersey, the Gateway Development Commission said Nov. 18, so both new rail tubes are now being dug.

The first machine started on the northern tube in October and has since cut about 400 feet and set more than 60 precast lining rings, according to the commission. The two are driving side by side for 5,100 feet, between the North Bergen portal and the Hudson County Access Shaft at the Weehawken-Hoboken line. The commission expects the stretch to take about a year, counting planned maintenance stops.

Both are single-shield machines built for hard, dry rock. Each has a cutterhead 28 feet, 8 inches across and trailing gear about 500 feet long that weighs more than 1,680 tons, ROI-NJ reported. Each will excavate and line the tunnel in the same cycle, placing close to 850 rings made from more than 5,000 concrete segments. ENR reported that six cross passages will connect the two tubes in this section.

Schiavone Lane Dragados JV is building the Palisades Tunnel package, one of the project's 10 construction contracts, and the bistate Port Authority runs delivery of that package together with the commission. When the machines reach the access shaft, crews will lift them out and bring in a second pair built for the mixed ground under the Hudson River. In April the commission awarded a $1.29 billion tunnel boring contract that ENR said completed procurement of the core tunneling work.

Commission CEO Tom Prendergast called the October start "only the beginning." The new tunnel will add capacity alongside the existing North River Tunnel, which is due for rehabilitation under the Gateway Program.

Why it matters: The Palisades drive gives the first real production rates on the $16 billion rail tunnel, and the river crossing waits on it. Segment, grout and haul suppliers and tunnel crews now have two headings running for about a year.