Gandara bridge collapse: two girders fall on Samar's P512 million parallel bridge project

Two girders fell on the P512 million Gandara Parallel Bridge project in Samar, Philippines, on Nov. 17 as crews took out a roller attachment. No workers were hurt, the Department of Public Works and Highways said.

The girders came down on Tuesday, Nov. 17, while a roller attachment was being removed, the Daily Tribune reported, citing a DPWH statement issued the next day. According to the department, the contractor reported no injuries. The DPWH has not named the firm.

Public Works Secretary Giovanni Lopez sent a technical team to the site to assess the damage and decide on corrective work. The agency said the contractor will face severe penalties if that assessment traces the failure to construction defects. It also said it would follow President Ferdinand Marcos Jr.'s order to keep workers on the site safe.

The contractor has accepted full responsibility, according to the DPWH, and has promised to replace the damaged girders without charging the government.

Gandara has been without its old crossing for years. The Gandara Bridge in the town center buckled in October 2020 under a truck carrying a crane, and in February then Secretary Vince Dizon ordered its P510 million reconstruction finished before the end of 2027, the Manila Bulletin reported. The DPWH has not said what caused the girders to fall or how the collapse affects the schedule.

Why it matters: Roller and bearing removal is a temporary condition where girders sit on changing supports. Bridge crews should check that their lift and bearing plans cover that step, and owners should note the contractor here is paying for the replacement girders.