FlatironDragados finishes $133 million section of Winston-Salem's Northern Beltway with seven bridges
FlatironDragados reached substantial completion on Nov. 9 on a $133 million eastern section of the Winston-Salem Northern Beltway for the North Carolina Department of Transportation, a job that built seven bridges, an interchange and over 1.5 miles of road.
The finished section ties U.S. 52 and the east and southeast sides of Winston-Salem to Interstate 40 and the existing stretch of I-74 toward High Point, according to the contractor's announcement as reported by Construction Owners Club. Drivers headed for those highways can now loop around the city instead of crossing downtown, and the work completes the I-74 corridor on the east side of Forsyth County.
When Flatiron announced the job in 2023, it described it as a $126 million, 1.5-mile extension between U.S. 311 and I-40 with five new bridges and repairs to three existing ones. The firm had already built a neighboring beltway segment worth $140 million. Flatiron said at the time that more than 100,000 vehicles a day pass through metropolitan Winston-Salem.
NCDOT opened new beltway sections between U.S. 421, I-40 and I-74 on a Saturday in September, two months ahead of schedule. The department said those two segments run about 3 miles, cost $387 million and were built from 2022 by prime contractors Webber and Flatiron Dragados. Their scope included 12 new bridges, a diverging diamond interchange at Kernersville Road and about 4 million cubic yards of earthwork. With them, NCDOT said, I-74 is complete through Forsyth County up to U.S. 52 north of the city.
Construction Dive puts the full Northern Beltway at $1.7 billion. Neither NCDOT nor the contractor gave a date for finishing the whole loop.
Why it matters: NCDOT still has more of the $1.7 billion loop to build. Bridge, earthwork and paving subs in the Triad should watch its lettings as crews and equipment come free from the finished eastern sections.