Megaprojects

FAA ground stop: L3Harris router upgrade under investigation as technicians' union says it was left out

The Nov. 13 nationwide FAA ground stop began while L3Harris was moving part of the agency's communications network from copper to fiber, Transportation Secretary Sean Duffy said. The union for FAA equipment technicians says its members did no risk review before the work.

Air traffic controllers at work at the Washington Air Route Traffic Control Center
Photo: U.S. federal government, via Wikimedia Commons, public domain

Duffy told reporters on Nov. 14 that an L3Harris crew at a remote FAA site was switching telecom lines from old copper wire to fiber when a router there was swamped with data, Fox Business reported. The trouble then spread to routers at other FAA sites. L3Harris, which has done telecom work for the FAA since 2002, owns the network the agency uses to control the airspace, Duffy said. He said investigators had not yet settled whether the cause was an installation error or a faulty router.

According to the FAA's own questions and answers, cited by Live and Let's Fly, the network was hammered with about 1,000 connection tries every 4 to 5 seconds. A new L3Harris router at a radio site in El Dorado, Arkansas, is under examination, along with equipment at a radar site in Amarillo, Texas. The agency got the network stable again by blocking those sites and shutting off a broadcast function on roughly 60 similar routers. All 22 Air Route Traffic Control Centers were hit, Paddle Your Own Kanoo reported, and the FAA says it will reconsider when this kind of maintenance is scheduled.

The Professional Aviation Safety Specialists union, which represents about 11,000 FAA and Defense Department technicians, said none of its members took part in the upgrade. Contractors have historically worked under a protocol in which FAA employees assess the risk and coordinate the maintenance, the union said. Duffy said on CBS that union technicians look after FAA-owned radios and radar, not the L3Harris network. L3Harris said more than 70% of the planned copper-to-fiber conversion is finished and that it is supporting the FAA's investigation.

Duffy is asking Congress for $50 billion to rebuild the air traffic control system. The FAA has said it needs 750 more certified technicians within three years; the union says little hiring has happened so far.

Why it matters: Cutovers on live systems are where a small job can shut down an operation. Contractors switching power, data or controls in occupied facilities should expect owners to ask for written risk reviews, owner sign-off and tighter work windows, and the FAA has already said it will revisit when such work is done.