MegaprojectsUK

Edmonton EcoPark incinerator contract rises to £1.25 billion as Acciona settles its claims

North London Waste Authority is raising Acciona's contract for the new Energy Recovery Facility at Edmonton EcoPark from £799 million to £1.25 billion and moving completion to December 2029, settling claims the contractor put at £572 million.

Acciona Industrial, part of the Madrid-based Acciona group, signed the deal in January 2022 with handover set for September 2026. Before the settlement it had been forecasting completion as late as 2032, arguing that client delays meant the finish date no longer held, Construction Enquirer reported. The authority, which handles rubbish for seven north London boroughs, rejected that view. Acciona was the only bidder to put in a final tender in the original procurement, according to New Civil Engineer.

Four disputes had gone to arbitration, NCE reported, citing a contract notice published on November 13. One concerned the requirement to work under NAECI, the national agreement that sets pay and conditions for engineering construction workers, along with local hiring and apprenticeship terms. The others covered design changes to the administration building, the design of a removable hood for the steam turbine, and the cost of a stay agreement that ran from June 2024 to January 2025. The authority said fighting them out would likely have taken years.

Under the new terms Acciona carries the risk of future inflation, NAECI wage rises, industrial relations and productivity. It will not face delay damages until six months past the new takeover date. Signing is planned for December 14.

The authority blamed much of the delay on a shortage of skilled subcontractors for mechanical and electrical packages such as boilers and flue-gas treatment. About £700 million has been spent and the plant is more than 60% built. The site went from roughly 200 workers at the start of this year to over 400, and the turbine and generator are in. Cancelling would have added about £100 million a year to the boroughs' waste bills by 2030/31, the authority said. The plant is sized for up to 700,000 tonnes of residual waste a year.

Why it matters: A design-build job that could not find M&E subcontractors ended in a 56% price rise and a three-year slip. Contractors bidding process plants under national labor agreements should price that labor and supply chain risk, which Acciona now carries here.