Ames Construction starts Denver's $12.7 million National Western Center pedestrian bridge over the N Line

Denver has started work on a pedestrian bridge from RTD's 48th and Brighton/National Western Center Station to the National Western Center campus. Ames Construction won the job with a $12.74 million base bid, about $3.3 million under the engineer's estimate.

The city and the Regional Transportation District marked the start at an event on Nov. 13, and heavy work began Nov. 16, Railway Supply reported. Construction is set to run through late 2027 while N Line commuter trains keep operating. The single-span bridge will cross the N Line and the tracks beside it; the U.S. Department of Transportation lists three sets, belonging to BNSF, the Denver Rock Island Railroad and RTD.

Each end gets a landing plaza with an elevator tower, which has its own HVAC, and a staircase. Ames is also responsible for lights on both plazas and inside the span, fiber for communications and security, a 10-foot sidewalk tying the east plaza into Brighton Boulevard and a 30-foot service road east of that plaza.

Bids opened Dec. 9, 2025. Ames offered $12,742,210 against an engineer's estimate of $16,020,381.42, and Flatiron Dragados came second at $16,102,891.71. An add-alternate of $900,000 would have taken the Ames total to $13,642,210, but the city council approved a contract equal to the base bid on Feb. 9, 2026.

Denver is paying for it together with a grant from the Federal Highway Administration. It counts among four pieces of the Reunited Denver Project in Globeville and Elyria-Swansea, which won a $35,475,000 federal Reconnecting Communities award; a 2024 city presentation set aside $10 million of that for the bridge. The start slipped from the spring date the National Western Center Authority had expected, and RTD's project card showed the schedule as delayed at the end of June.

Why it matters: Ames bid about 20% under the engineer's estimate on a job built over three active rail lines with N Line service running throughout. Elevator, lighting, fiber and sitework subs have work on this site through late 2027.