Darlington SMR will run over its C$7.7 billion budget and miss its 2030 start, Ontario Power Generation says
Ontario Power Generation said on Nov. 10 that the first small modular reactor at its Darlington site east of Toronto, a GE Vernova Hitachi BWRX-300, will not start commercial operation by October 2030 and will cost more than its C$7.7 billion (US$5.4 billion) estimate. No new cost or date has been set.
OPG tied the slip to GE Vernova Hitachi's engineering on the first unit of its design, which the utility said is still unfinished and is hurting construction and supply-chain performance, World Nuclear News reported. OPG expects to substantially complete a full review of cost and schedule by mid-2027. The C$7.7 billion figure covered Unit 1 plus the systems all four planned reactors will share.
A GE Vernova Hitachi spokesperson told Canary Media that engineering, procurement and construction all played a part, along with inflation and geopolitical risk. It is the project's second delay: when OPG picked the design in late 2021, it said the first reactor could be finished as early as 2028, Canary Media reported.
Work on site continues. The basemat module for the reactor building was set 35 meters (about 115 feet) down the excavated shaft in April, and long-lead parts such as the reactor pressure vessel are already bought, according to World Nuclear News. Ontario approved C$20.9 billion for all four units in 2025. In a Nov. 10 rate filing with the Ontario Energy Board, OPG removed the reactor's planned output for 2030 and 2031, CleanTechnica reported.
The same reactor is planned in the US. The Tennessee Valley Authority received an NRC construction permit for a BWRX-300 in September, and Blue Energy has begun the NRC application process for one in Texas, Canary Media reported.
Why it matters: The first BWRX-300 shows what happens when building starts before the vendor's design is done. Contractors pricing US units for TVA or in Texas should ask how much engineering is finished and who carries design-change risk.
Sources
- OPG set to revise timeline and cost of first SMR unitWorld Nuclear News, Nov 11
- Leading small modular nuclear reactor will be late and over budgetCanary Media, Nov 11
- Darlington SMR Cost Overrun Exposes Ontario's Four-Reactor RiskCleanTechnica, Nov 15