Bathla administration: receivers take over Lochinvar estate as nearly 50 buyers wait with no restart date
Receivers Mackay Goodwin now control Bathla Group's Windermere Road estate at Lochinvar, west of Maitland, where almost 50 households signed up for houses, the Newcastle Herald reports. Building has stalled and nobody has set a date to restart.
The receivers are working out what to do with the estate, including where existing contracts stand and what choices buyers have, the Herald reported on November 17. Some buyers have put down deposits in the tens of thousands of dollars. Many are paying rent while they wait.
Bathla Group, a Sydney developer that trades mainly through Universal Property Group, went into voluntary administration on August 25. Its administrator is Teneo Financial Advisory Australia. Teneo has told customers it is going through the developments one project at a time and wants to finish current jobs where it can, the Herald understands. It has not given dates for individual homes. The NSW Supreme Court has given the administrators until September 2027. That extra time is no guarantee for any single project.
Trades are out of pocket as well. Some contractors told the Herald they are owed close to A$400,000 across several Bathla jobs. The main entity reported A$3.2 billion in liabilities at June 30, 2025, mostly reportedly owed to private credit funds. In late August the court heard the administrators expected to burn about A$40 million in cash between September and December.
One Lochinvar buyer told the ABC she paid A$709,990 in mid-2025 for an off-the-plan house. She was promised it by June, then August, and the date has since slipped to the end of this year. Decisions on Lochinvar contracts now rest with the receivers. Whether other Bathla projects get finished is up to the administrator.
Earlier: Builders wary of finishing collapsed developer Bathla's half-built Sydney homes
Why it matters: For trades owed money on Bathla jobs, the first question is who controls each site. On receivership estates such as Lochinvar, decisions on existing contracts sit with Mackay Goodwin, not Teneo, so claims and questions go to the receiver.