Edition
Sunday, November 22
Updated
1:06 PM EST

Fails & scandalsGreece

Athens Metro Line 4 damage: a Kypseli footing no longer rests on the ground, and the mayor seeks evacuation

An engineer advising residents of Kypseli in central Athens told the city council that one footing of the apartment block at 92-94 Spetses Street has lost contact with the soil after Metro Line 4 tunneling, so a small earthquake could do serious harm. Mayor Haris Doukas says he is asking for the building to be emptied.

Tunneling for Line 4 between Kypseli station and Dikastiria has been halted since May 8, after monitoring recorded more ground settlement than expected and cracks opened in nearby apartment blocks, Greek City Times reported. Inspectors from the Technical Chamber of Greece have since rated some buildings red, including the one at 92-94 Spetses Street, close to where the tunnel boring machine stopped.

At the council session, structural engineer Nikos Krasakis said the strengthening work now going on is a stopgap that leaves the underlying damage unrepaired, To Vima reported. The residents' lawyer, Thanasis Kambagiannis, showed a November 12 letter from Elliniko Metro, the state company building the line, about restoring support under the footings. He also cited a contractor email that spoke of work to remove an immediate danger at building 513, the Spetses Street block.

Elliniko Metro said on November 16 that the technical findings gave no reason to move people out because of the buildings' condition, and that residents would be relocated only where the work made it impossible to stay. Doukas, an engineer, wrote to the company the same day asking it to rehouse everyone in the red-rated blocks at its own and the contractor's cost. He also objected that crews began pouring asphalt and concrete at one building before residents were told and before the technical studies were presented.

Lord Robert Mair, the British engineering professor appointed to review the case, is expected to report around mid-December. Deputy Infrastructure Minister Nikos Tachiaos has said boring will not resume before 2027, once safety checks are done.

Why it matters: Tunneling under older buildings on shallow footings is where settlement monitoring and pre-construction condition surveys earn their cost. US transit and utility contractors can look at how alarm thresholds, red tags and resident relocation get decided here, and settle those rules before their own machine starts moving

Sources

More in fails & scandals