Winnipeg could hit its sewage sludge treatment limit in late 2029, a year before new biosolids plant helps
Winnipeg has room to treat sewage sludge for roughly 25,000 to 35,000 more people-equivalent and could reach the limit as early as late 2029, says a city report released Tuesday. New biosolids facilities at the North End plant are due to start treating in October 2030, the Winnipeg Free Press reported.
The annual capacity report was written by Cynthia Wiebe, manager of engineering services in the city's water and waste department. Real headroom can swing from one year to the next, the report says, with how fast the city grows, which industrial plants connect and how big they are, and chemical treatments that alter how much sludge is produced. The department first raised the alarm in late 2020, giving the biosolids plant a horizon of five to nine years before it filled up, and it has issued a fresh estimate every year since.
The new biosolids facilities are the second phase of a $3.1 billion upgrade of the North End sewage treatment plant on Main Street. Construction on that phase began in August, and the facilities should be fully commissioned in 2031, according to the Free Press. On Oct. 30 the federal, provincial and city governments agreed to share the cost of the third and final phase.
Mayor Scott Gillingham said the city is not considering any limit on development and that he is confident staff can close the gap. Wiebe said crews are pulling more grit, grease, oil, rags and sand out of the flow before it reaches the digesters. Better screening is already working at the North End plant, and the West End plant is due for the same upgrade in about two years. Testing will show how much room those steps actually free up, and the city is drawing up contingency plans, she said.
Why it matters: Treatment capacity decides how many new homes and plants Winnipeg can connect. Developers and industrial clients planning to hook up in 2029 and 2030 should follow next year's capacity update and the West End screening work.