Pillars of a church pavilion under construction collapse near Accra as workers unload cement
Pillars of a structure under construction at Breaking Yoke Ministry in Klagon, near Lashibi in Greater Accra, gave way on Oct. 28 while about eight men were unloading cement. Local media reported two people hospitalized; the church says no one was hurt or trapped.
Witnesses told GhanaWeb the crew was hauling cement up to a higher level of the building when it gave way. Early reports said two injured workers were taken to hospital and residents feared others were under the debris. Ghana National Fire Service crews went to the site. Video by blogger Sammy Kay Media, described by DailyGuide, showed formwork, timber scaffolding and mesh brought down near the top of the multi-storey frame, with rebar exposed.
Breaking Yoke Ministry International said in a Facebook statement that the main church is intact, that an isolated structure was affected and that there were no casualties and no one trapped, YEN.com.gh reported. The church's Pastor David told the blogger that what fell was a pavilion the church was building so members would have cover after services.
He also gave his account of the cause. The church had raised the pavilion's pillars and planned to cast beams to tie them together, he said, but the company doing the work chose to pour everything at once with ready-mixed concrete, and the fresh beams failed to brace the columns since the concrete had not yet set. YEN said it could not verify his claims. Authorities have not confirmed a cause, and the contractor has not been named.
In March, an unfinished building in Accra New Town that was being used as a church collapsed after heavy rain and killed three people, DailyGuide reported. In Uganda, inspectors said this week that a church extension that collapsed in Wakiso district had no permit.
Why it matters: Stacking cement on a frame whose beams were cast together with the columns and have not cured puts the load on green concrete and temporary formwork. Keep materials off new concrete until the engineer's stripping and loading schedule allows it.
Sources
- Fear grips Klagon residents as church building collapses on workers - ReportsGhanaWeb, Oct 28
- Pastor David Breaks Silence on Breaking Yoke Church Building Collapse, Explains What HappenedYEN.com.gh, Oct 29
- Church Building Collapse: 8 Trapped, Two In HospitalDailyGuide Network, Oct 29