Dodge sees US construction starts falling 5.4% in 2027 after a data center-driven 2026

Dodge Construction Network expects total US construction starts to climb 10.9% this year to $1.424 trillion and then drop 5.4% to about $1.348 trillion in 2027, according to forecast tables ENR published Nov. 18. Data centers account for most of the growth.

Office starts, the Dodge category that counts data centers, are set to jump about 58% in 2026 to $182.8 billion and ease 4.9% next year. The deepest 2027 declines are in power plants, gas and communications, down 31.8% to $107 billion as the wave of LNG plants that broke ground in 2025 and 2026 passes, and in manufacturing, down 29.6% to $47.5 billion. Single-family starts go the other way, up 5.5% to $240 billion after slipping 1.8% this year. Dodge also sees warehouses up 9.6% and health care facilities up 7.5%.

Sarah Martin, Dodge's director of economic research, told ENR that inflation will be the main pressure in 2027. With oil above $100 a barrel, Dodge expects construction materials inflation to top 9% around the turn of the year before it starts to ease. She said higher material costs and worse labor shortages fall hardest on smaller projects, while megaprojects carry nonresidential work.

FMI's spending forecast shows the same split. It puts 2026 construction put-in-place near $2.17 trillion, 3.4% under 2025, while data center spending grows 49% this year and another 37% in 2027. FMI partner Jay Bowman told ENR the market feels soft once you look past the AI build-out. ConstructConnect chief economist Michael Guckes said mid-size and small firms that can't lead billion-dollar jobs may get their share by teaming with the contractors that do.

Elsewhere in the outlook, the National Association of Home Builders expects total housing starts to fall 4% in 2027, and ARTBA sees highway work rising 0.9% to $121.7 billion.

Why it matters: If your backlog leans on factory, power or LNG work, 2027 starts point to fewer new jobs. Single-family, warehouses and health care look steadier, and for most subs the way onto data center work runs through the few large GCs that hold it.