Data center cancellations more than doubled in the third quarter as local boards voted projects down, Relae says
Local opposition halted 16 proposed US data centers between July and September, against seven in the same months of 2025, Relae reports. It counts about $64 billion in planned investment lost in the quarter and roughly $271 billion across 70 stopped projects since January 2024.
What changed is who does the stopping. Local governments ended 11 of the 16 projects with a formal denial or a zoning ban, Relae said in its Nov. 17 report: seven denials and four bans, up from two denials and one ban in the second quarter. Developers pulled the other five. Before this quarter, a developer walking away, often right before a hearing, was the most common end.
Virginia had three of the quarter's 16 projects, and seven were in the PJM grid region. Of the $271 billion total, $183 billion comes from publicly disclosed figures; the rest is Relae's estimate.
In 44 cases it studied in depth, Relae found transparency and process to be the top complaint in 19. Arguments about NDAs and undisclosed developers turned up in 31 cases. Energy costs and the grid were a leading or secondary theme in 29. Water use came up in 32 cases but led in only one, in San Marcos, Texas. Of 47 local ballot measures on data centers this election cycle, the 46 that passed all limited or banned development.
State agencies in Virginia can no longer sign or demand some kinds of secrecy agreements on data center deals, Relae notes, and it expects another state to file a comparable bill by year-end. It also expects denials and zoning bans together to outnumber developer withdrawals again in the fourth quarter.
Why it matters: A data center job can now die at a zoning vote after design and preconstruction money is spent. Before committing crews or buying long-lead gear for one, check its zoning status, any pending local ballot measure and whether the end user has been named.
Sources
- Community Signals Q3 2026: Data Center Cancellations Double as Local Governments Step InRelae, Nov 17